Old Fold Estate
The Challenge To support Gateshead Council’s decarbonisation plan with a pilot project to transition the first 16 of 600 properties from gas to the Gateshead
The PPSL District Heating team is immensely proud of our work – delivering excellence in every project. With a “right first time” approach to everything we do, we strive to provide the best customer service in the sector. Here are some recent examples of how we have helped our clients deliver their district heating projects and most importantly, what they think of PPSL.

The Challenge To support Gateshead Council’s decarbonisation plan with a pilot project to transition the first 16 of 600 properties from gas to the Gateshead

The Challenge To replace an aging and failing steam system in a space-constrained area of the hospital which was surrounded by live wards. The design

The Challenge To install more than 1km of mainly 350/630mm pre-insulated pipe at a university campus during term time. Not only did we have to

The Challenge To supply and install a network in a secure prison environment. PPSL was tasked with locating the existing network and designing new pipework

The Challenge Acting as principal contractor, PPSL was challenged to extend a 200/355mm district heating main, fibre and HV network by 2km via highly congested

The Challenge Our client FES Group was appointed by principal contractor Multiplex to deliver a new project for the University. FES Group tasked PPSL with

The Challenge A previous contractor had installed conventional valves below the ground across the whole of the Bath University site whilst installing a new heat

The Challenge To replace the site wide heat network at the base while minimising any disruption to day-to-day activities. This project would involve connecting to